Implementation

The following table highlights the key actions and timings for the recommendations in this report. MOU funding ceases at June 30 2013.

Table 1 Implementation of key actions
Recommendation Timeframe Slippage risk
1 - Develop classification management principles August 2012 to November 2012 Low
2 - Update Classification Rules January 2013 to June 2013 Low
3 - Develop APS-wide WLS August 2012 to June 2013 High
4 - Develop role evaluation methodology and tool December 2012 to June 2013 High
5, 6, 7, 8- Develop classification guide and improved policy guidance September 2012 to June 2013 High